Skip to content

New building law and permit conditions

What the authorities can demand and when they go too far

Obtaining a building permit does not necessarily mean that the developer is in the clear. The permit may contain a number of conditions, the fulfillment of which can affect the course and costs of the project. Although the new Building Act (Act No. 283/2021 Coll.) has changed the building permit process, the power of building authorities to set conditions remains in place. In this article, we will therefore explain what conditions the building authority can set in the permit, where the limits of its power lie, and how to proceed if it requires more than the law allows.

The New Building Act and Permit Conditions

Key takeaways

The building authority may stipulate a number of specific conditions in the permit – for example, regarding site safety, technical execution, construction deadlines, transport connections, or the future use of the building.
However, the authority cannot demand just anything. The conditions must have a basis in law, relate to the permitted construction, and protect a legitimate public interest. For instance, it cannot condition the permit on a financial contribution to the municipality or the construction of unrelated infrastructure.
The conditions must be specific, intelligible, and feasible. Vague requirements that do not clearly state what the developer is expected to do may be unlawful and can be challenged in practice.
An unlawful or unreasonable condition can be challenged by filing an appeal. It is advisable to address this promptly – according to the article, the standard time limit for an appeal is 15 days from the delivery of the decision.
For a developer, it is crucial to continuously monitor the conditions and document their fulfillment. If a problem arises, it is better to communicate with the authority and potentially request a change in the conditions rather than ignoring them and dealing with the issue only at the final building approval stage.
ARROWS law firm

What conditions can the building authority impose?

Technical and safety requirements during construction:

The authority can stipulate how to secure the construction site to prevent endangering the surroundings (e.g., securing excavations, limiting dust or noise, protecting nearby trees, etc.). It also imposes the obligation to adhere to specific technical standards and procedures according to the project documentation and the binding opinions of the relevant authorities (fire department, public health office, heritage conservationists, etc.) to ensure everything complies with regulations. For example, it may specify the stages at which you must consult with a structural engineer or that you must allow archaeologists to supervise earthworks.

Deadlines and construction organization:

The building authority typically sets a deadline for the commencement and completion of construction. The new Act has introduced a simplification here – the permit generally expires if construction does not begin within a certain period, and once construction starts, the permit is valid for up to 10 years. However, authorities often add an indicative deadline for completion. They do this to prevent a half-finished project from lying dormant for many years. Furthermore, the permit may contain organizational instructions, such as the requirement to carry out construction continuously and without unnecessary delays. If you are building yourself (which is uncommon for development projects), the authority will also name a qualified person in the conditions to provide professional supervision of the construction.

Specific requirements for the appearance and connection of the building:

In justified cases, the building authority may also resort to more detailed conditions. For example, imposing a specific aesthetic or urban planning requirement – typically modifying the facade, choosing the plaster color, or the shape of the roof, if this arose from a binding opinion of architects or heritage conservationists. It also often sets conditions for traffic connections: it can order the construction of a certain type of access road, the installation of temporary traffic signs during construction, etc. These conditions ensure that the building integrates appropriately into its surroundings and does not jeopardize traffic flow.

Conditions for the future use of the building:

In addition to conditions on "how to build," the authority can also specify "operational" conditions before you receive the final approval for use. For example, for noisy operations, it can impose an obligation to conduct noise measurements before the final approval and submit the results to the public health office. For large complexes, the authority sometimes requires a trial operation – meaning you will use the building in a test mode for a certain period and monitor aspects like emissions, traffic load, etc. All this is again aimed at protecting public interests, such as public health, the environment, or traffic flow.

These conditions are not arbitrary: they are based on the documents of expert bodies and standards. The new Building Act has even introduced a rule that many specialists no longer issue separate opinions but directly formulate their part of the decision – i.e., the relevant permit conditions falling within their competence. Ideally, the building authority thus acts as a coordinator, incorporating conditions from the relevant authorities into the permit and supplementing them with its own requirements as mandated by law.

In summary: Expect the building permit to contain a series of specific instructions on when, what, and how to do things during construction. They are intended to protect public interests and ensure your project proceeds in accordance with legal regulations. For a developer, these conditions are a de facto checklist that must be followed – from the start of construction to its final approval for use.

What are the limits of the authority's powers?

However, the building authority cannot order just anything. Its power is limited by law – the authority may only impose conditions that are supported by legal regulations and are related to the permitted construction. It is crucial to know these limits, as it sometimes happens that the authority (knowingly or unknowingly) goes too far with its demands.

1. Conditions must serve to protect legitimate public interests. Therefore, the authority cannot impose something that is unrelated to the project or does not represent a legitimate public interest. For example, it cannot demand from an investor a performance that is effectively outside the scope of the Building Act – typically financial contributions to the municipality, donations, or other investments not directly related to the construction.

A building permit should not include the assessment of a fee (e.g., an administrative or local fee) or make the permit conditional on concluding a contract with the city. Such requirements are beyond the scope of the building authority's power. If a municipality needs a contribution from a developer for infrastructure (a kindergarten, park, etc.), it should be handled through a separate planning agreement, not through permit conditions – the building authority has no legal authorization for this.

2. Conditions must not contradict other decisions and regulations. The authority cannot use conditions to change what has already been approved in a zoning decision or demand something that contradicts the binding opinions of the relevant authorities. For example, if the zoning decision specified a certain road connection, the building permit cannot "override" it with a different condition.

Likewise, it cannot ignore a binding opinion – if the public health office permits operation without air conditioning, the authority cannot impose the opposite on its own. However, it can, of course, adopt and specify the conditions proposed by the relevant authorities. The limit is that the building authority is not a superior body for specialized requirements – it is a coordinator, not a dictator in matters outside its expertise. On the contrary, the building authority is bound by the content of binding opinions and must not deviate from them.

3. Conditions must be specific, feasible, and understandable. Vague or ambiguous conditions are problematic – if you don't understand them, the officials won't be able to check them during the final approval process either. For example, stating that you must "limit dust as much as possible" is not specific. The condition must say how to achieve this (e.g., by regularly watering the construction site).

Unclear conditions can even be considered illegal because they are unenforceable and unreviewable. In practice, it has actually happened that a court annulled a decision due to a condition that was formulated so vaguely that it was unclear what exactly the builder was supposed to fulfill. As a developer, you have the right to request clarification – and the authority has an obligation to formulate conditions unambiguously.

4. The authority cannot circumvent the law through conditions. Sometimes, suspicion may arise that an official is using conditions to achieve something that the law does not directly allow. Example: If the law does not explicitly set a deadline for construction completion, the authority should not arbitrarily shorten it to an unreasonably short period. (Historically, decrees set a two-year deadline, but courts pointed out that the law did not grant such authorization.)

The new Act now states – start construction within two years, and after commencement, you have up to ten years to complete it. If the authority were to demand completion within, for example, two years for a large complex without legal basis, it would be exceeding its powers. Such a condition could be challenged for illegality. Generally, permit conditions cannot replace penalties or transfer responsibility to the builder for broader issues in the area unless there is a legal reason to do so.

DO YOU NEED LEGAL HELP?

Get in touch — we're happy to help.

ARROWS law firm

When the authority goes too far: a case study from practice

Let's look at a specific scenario that occurred in recent practice and show how a developer can defend themselves. Development company XYZ applied for a building permit for a residential complex in one of the city districts. The building authority made the issuance of the permit conditional on the developer building a public children's playground and a park on an adjacent municipal plot at its own expense. This requirement was not part of the original project – it arose from pressure from the local government, which wanted to improve public amenities in the area. The developer initially agreed, not wanting to delay the permit process. However, their lawyers warned them of the risks of such a "gift."

It's not just about the additional cost in the millions of crowns. The main problem is that such a condition is outside the building authority's jurisdiction and potentially illegal. In the described case, there was even a risk of what courts have warned about in the past: when a city district accepts such a gift from a developer, the building authority of that same district may be considered biased when permitting the construction.

Opponents of the project could argue in court that the authority was not impartial (because the city hall got a park) and have the entire permit annulled. This is not a theory – the "something for something" practice has already led to the annulment of zoning or building decisions, and developers must be wary of this. In our case, therefore, the legal representatives recommended: do not sign any agreement to build a park as a condition of the permit, as it would jeopardize the entire project.

Our specialists will help you

JUDr. Ondřej Stehlík, LL.M., MBA

JUDr. Ondřej Stehlík, LL.M., MBA

advokát, partner

stehlik@arws.cz
JUDr. Jakub Dohnal, Ph.D., LL.M.

JUDr. Jakub Dohnal, Ph.D., LL.M.

advokát, řídící partner

dohnal@arws.cz
ARROWS law firm

The developer ultimately filed an appeal against the building permit regarding the part concerning the disputed condition. The superior building authority (under the new system, either the regional authority or the Specialized and Appellate Building Authority) reviewed whether the requirement to build the park was lawful. It concluded that it was not – such a condition has no basis in the Building Act or any other regulation and is not directly related to the construction project itself.

It therefore annulled the condition and confirmed the building permit without it. The result? The developer not only avoided additional expenses but also prevented the possible judicial annulment of the entire permit due to the authority's bias. The case also showed other investors that it makes sense to defend themselves when official requirements exceed legal limits.

This case study illustrates that even in current practice, situations arise where building authorities (often in agreement with local governments) set conditions that are on or over the edge of their competencies. A developer who is unsure about the legality of the requirements should not hesitate to involve lawyers and seek defense through legal remedies. 

Indeed, every month of project delay or extra million spent on "something extra" can mean a significant blow to the business plan – and often unnecessarily.

DO YOU NEED LEGAL HELP?

Get in touch — we're happy to help.

ARROWS law firm

Practical tips for developers: how to handle conditions in the building permit process

Based on the above, here are practical tips to help you, as a developer, manage building permit conditions without harm:

  • Involve a lawyer from the project preparation and application stage. A qualified legal audit of the project documentation before submitting the application can identify potentially contentious requirements before they are "set in stone" in the permit. A lawyer will also ensure that the proposed solution complies with all regulations – thus preventing a situation where the authority imposes strict conditions later because something was not in order.

  • Carefully read every decision and its conditions. Once you receive the building permit, study the operative part and the reasoning in detail. If you don't understand a condition or it seems unreasonable, consult a lawyer or project designer immediately. Don't downplay "strange" wording – what is vague to you will also be vague to the inspectors at the final approval stage (and that's a problem). If in doubt, request clarification or an amendment to the condition.

  • Use legal remedies in a timely manner. Under Czech legislation, you can defend against conditions – most commonly through an appeal within 15 days of receiving the decision. The appellate body can change or annul the disputed condition without jeopardizing the entire permit. Don't be afraid of "angering" the authority – this is a standard procedure. It would be worse to passively accept an illegal condition and then fight it during construction. In extreme cases (if an appeal doesn't help), you can also defend yourself with a lawsuit in court.

  • Document the fulfillment of conditions. Take the conditions that remain in the permit seriously. Create an internal checklist of who will fulfill what and when. Keep a detailed construction log – record how you fulfilled individual obligations (securing the site, noise measurements, tests, etc.). At the final approval stage, you will need to prove that you have met all conditions, and well-kept documentation will save you time and stress.

  • Communicate with the authority proactively. If you encounter an obstacle in fulfilling a condition (e.g., a supplier is missing a deadline or an objective problem arises), inform the building authority in a timely manner. You can request a change to the construction before completion or an extension of deadlines if you have valid reasons. Ignoring a condition and "hoping it will pass" is a recipe for trouble – authorities will notice it during the final approval or inspection, and you risk penalties. Open communication and a potential request to amend the decision is a better path.

Conclusion: Don't underestimate the legal side and protect your investment

A building permit with its conditions is a milestone for every development project. It can signal a smooth implementation – or become a source of delays and disputes if it contains ambiguities or illegal requirements. As developers, you are under pressure from deadlines and budgets, but that is precisely why it doesn't pay to underestimate the legal side of things. A single disputed condition can, in an extreme case, jeopardize the entire permit and cause additional costs or losses (for example, if a court were to annul the permit at a competitor's instigation due to a procedural error).

The good news is that with quality legal advice, most problems can be prevented. A lawyer knowledgeable in Czech construction law will help you set up the project so that authorities have no reason to impose excessive conditions, and will ensure that the authority stays within the limits of its powers. If a disagreement does arise, they will advise on an effective defense. This proactive approach can save you months of delays and hundreds of thousands of crowns, not to mention your peace of mind.

A call to developers: Don't wait for a problem to arise. Consult on your construction plans early – ideally even before submitting the permit application. The investment in legal certainty is negligible compared to the value of the project it protects. You will then sleep soundly knowing that your project is being watched over not only by architects and engineers, but also by legal guardian angels. And that is a priceless certainty in the uncertain world of building proceedings. Your construction will thus grow on a solid foundation without unnecessary legal tremors – and that is exactly what it should be about. In the construction business, it is doubly true: fortune favors the prepared.

FAQ - The New Building Act and Permit Conditions

1. What conditions can the building authority set in a permit?

It can set requirements for construction site safety, technical execution of the building, organization and deadlines for construction, traffic connections, or conditions for the future use of the building.

2. Can the building authority demand anything it deems necessary?

No. Conditions must be based on legal regulations, be related to the permitted construction, and pursue a legitimate public interest. For example, the authority cannot make a permit conditional on a financial contribution to the municipality or the construction of unrelated infrastructure.

3. What requirements must the authority adhere to for permit conditions?

Conditions must be specific, understandable, and feasible. Vague requirements where it is unclear what exactly the builder must fulfill can be illegal and unreviewable.

4. What should I do if a building permit condition is illegal or unreasonable?

You can defend against such a condition primarily through an appeal. The standard deadline for an appeal is 15 days from the delivery of the decision. In extreme cases, judicial protection can also be sought.

5. How should a developer work with building permit conditions?

It is advisable to thoroughly check the conditions before starting construction, continuously document their fulfillment, and communicate with the building authority in a timely manner if problems arise. If a condition is contentious, it is better to address it immediately rather than waiting for a problem during the final approval process.

DO YOU HAVE MORE QUESTIONS? GET IN TOUCH

ARROWS law firm

About the author

JUDr. Lukáš Slanina
JUDr. Lukáš Slanina

Associate, partner

Lukáš Slanina as one of the partners and attorney at ARROWS focuses mainly on providing legal support to real estate agencies and their preparation for the new real estate law. He leads a team that deals with contractual documentation for real estate transfers, all contractual matters related to the functioning of real estate agencies and successfully represents real estate agencies in court disputes with dishonest clients. He regularly provides legal training for real estate agents.

Disclaimer:

The information contained in this article is for general informational purposes only and serves as a basic guide to the issue as of 2026. Although we strive for maximum accuracy, laws and their interpretation evolve over time. We are ARROWS Law Firm, a member of the Czech Bar Association (our supervisory authority), and for the maximum security of our clients, we are insured for professional liability with a limit of CZK 350,000,000. To verify the current wording of the regulations and their application to your specific situation, it is necessary to contact ARROWS Law Firm directly (consultation@arws.cz). We are not liable for any damages arising from the independent use of the information in this article without prior individual legal consultation.